Beacon Data Centers paid for the study of the proposed Spruce Lake data centre; the company is advancing the proposal with U.S.-based VoltaGrid. According to CBC, the two companies have proposed a large data centre complex in Saint John, New Brunswick, though the project remains proposed.
According to GlobalNews Canada, Mayor Donna Reardon said projected revenue could help repair aging pipes and roads, improve transit and parks, and potentially reduce residents’ taxes. According to CBC, Reardon said the city had bought little new equipment in recent years because of a structural budget problem, and that the proposed revenue could improve services.
According to CBC, Beacon and VoltaGrid’s plan calls for four buildings spanning 1.5 million square feet, alongside a 190-megawatt natural-gas generating station. According to GlobalNews Canada, the proposed facility would take power from NB Power and also produce electricity on site through natural-gas generation, Global News reported.
According to GlobalNews Canada, Consultant David Campbell’s estimate included land, buildings and power infrastructure, but he said the final assessment might vary by several million dollars in either direction. According to CBC, Campbell said most project spending would go toward machinery and equipment, which is not taxable in New Brunswick, while $1 billion in buildings and improvements could produce a large tax bill.
According to GlobalNews Canada, Service New Brunswick assesses properties using factors including land, building size, construction, age, condition, replacement costs and market values. According to CBC, Campbell said Service New Brunswick would set the final taxable value of the completed project, which could differ from his estimate.
In a written response to CBC, Beacon said it expected the project to make a substantial contribution to local and provincial tax bases, without endorsing Campbell’s estimate. According to GlobalNews Canada, Beacon told Global News that projected benefits depended on regulatory approvals and construction, while authorities would determine the final property assessment and tax bill.
CBC reported that Beacon commissioned and paid Campbell, whose study examined the proposal the company is developing with VoltaGrid. The Irving Oil Refinery paid Saint John $2.94 million in property taxes that year, making it the city’s largest private-sector property-tax bill, CBC reported.
CBC reported that the estimated city tax payment from the proposed development would equal property taxes paid by eight large oil refineries. According to GlobalNews Canada, opponents have raised environmental and health concerns, with Save Lorneville member Chris Watson questioning the development’s noise and air-quality testing.
According to GlobalNews Canada, Watson said his community believed no dollar amount could compensate for what it would lose if the project went ahead. According to CBC, At an open house earlier that month, opponents raised concerns about environmental effects and quality of life, particularly in the neighbourhood where the project is proposed.
Adam Wilkins, a development critic quoted by CBC, said no amount of community benefits would justify pollution or harm to health and well-being.
Reader comments (0)
Bring evidence, ask questions, or challenge our reporting. Every comment is checked before publication.
No approved comments yet
Be the first to ask a thoughtful question or contribute useful context. We won't invent reader conversations.
Join the discussion
Members-only commenting
Everyone can read comments. To write, verify your email and sign in to your free member account.